NVS-04 Launch Date & GSLV-F19 Status

NVS-04, also designated IRNSS-1M, is the next satellite in NavIC, India's own satellite navigation system. ISRO has not announced a launch date. What it has confirmed is the rocket and a first milestone: on 5 November 2026 the cryogenic engine for GSLV-F19, the vehicle that will carry NVS-04, passed its flight acceptance test at the ISRO Propulsion Complex in Mahendragiri.

The test ran for 200 seconds. ISRO's statement of 10 November 2026 says the main engine and the gas generator ignited as expected and that performance was satisfactory and consistent with pre-test predictions. The engine will now be inducted into the cryogenic stage of GSLV-F19. Public launch listings place the flight in 2027, but that is a listing, not an ISRO announcement.

NVS-04 is a navigation satellite: it broadcasts precisely timed signals that receivers on the ground use to work out position and time. It belongs to the second-generation NVS series, which adds the L1 band used by phone chipsets to NavIC's L5 and S-band signals and flies an atomic clock developed in India. It follows NVS-03, launched on 30 October 2026.

Frequently asked questions

When is the NVS-04 launch date?

ISRO has not announced a launch date for NVS-04. As of November 2026 the only confirmed milestone is the flight acceptance test of the GSLV-F19 cryogenic engine on 5 November 2026. Public launch listings show the mission in 2027 with the status 'to be determined', and Indian press reports also expect 2027. This page will carry the date once ISRO publishes one.

What is the NVS-04 launch time?

No launch time exists yet, because no launch date has been set. ISRO normally publishes the exact lift-off time a few days before a GSLV flight. The earlier NVS satellites all flew from the Second Launch Pad at the Satish Dhawan Space Centre, Sriharikota, and launch listings give the same pad for NVS-04.

What is the full form of NVS-04?

NVS is ISRO's name for its second-generation NavIC navigation satellite series. NavIC stands for Navigation with Indian Constellation. The 04 means it is the fourth satellite in the series, after NVS-01 (2023), NVS-02 (2025) and NVS-03 (2026). Its other name, IRNSS-1M, comes from the older Indian Regional Navigation Satellite System numbering.

Is NVS-04 the same as IRNSS-1M?

Yes. NVS-04 and IRNSS-1M are two names for the same satellite. NVS-04 is its designation in the second-generation NavIC series. IRNSS-1M is its name in the original Indian Regional Navigation Satellite System sequence, which runs from IRNSS-1A in 2013. Launch listings usually print both, as 'IRNSS-1M (NVS-04)'.

What does the NVS-04 satellite do?

NVS-04 is a navigation satellite. It carries atomic clocks and broadcasts timed signals in the L1, L5 and S bands; a receiver that hears at least four such satellites can calculate its position and the time. NavIC offers a Standard Positioning Service open to everyone and an encrypted Restricted Service for authorised users such as the armed forces. ISRO states NavIC's accuracy as better than 20 metres in position and better than 40 nanoseconds in time, across India and about 1,500 km beyond its borders.

What engine did ISRO test for GSLV-F19?

The cryogenic engine that will power the upper stage of GSLV-F19. ISRO carried out its flight acceptance test on 5 November 2026 at the ISRO Propulsion Complex in Mahendragiri. The engine fired for 200 seconds. ISRO reported that the main engine and gas generator ignited as expected and that performance matched pre-test predictions. The engine burns liquid hydrogen with liquid oxygen.

What is a flight acceptance test?

It is the ground firing every flight engine must pass before it is fitted to a rocket. A development test proves a design; an acceptance test proves one particular engine. The engine is fired on a test stand and its measured behaviour is compared with predictions. Passing clears that engine for flight. For GSLV-F19, the next step ISRO has named is inducting the engine into the cryogenic stage.

Which rocket will launch NVS-04?

GSLV-F19. GSLV stands for Geosynchronous Satellite Launch Vehicle. It is a three-stage rocket of about 420 tonnes: a solid core with four liquid strap-on boosters, a liquid second stage, and an Indian-built cryogenic upper stage. The same vehicle class launched NVS-01, NVS-02 and NVS-03. GSLV-F18, the previous flight, was the twentieth GSLV launch.

Why does NavIC need NVS-04?

Because NavIC has been running with very few working navigation satellites. A position fix needs at least four. For most of 2026 only three — IRNSS-1B, IRNSS-1I and NVS-01 — were in navigation service, after most first-generation satellites lost their atomic clocks and NVS-02 was stranded in 2025. NVS-03 is meant to be the fourth. NVS-04 would be the fifth, which gives the system a margin: with exactly four, the loss of any one satellite ends the service.

Where will NVS-04 be placed in orbit?

ISRO has not published the orbital slot for NVS-04. NavIC satellites sit about 35,786 km above the equator, some in geostationary orbit and some in geosynchronous orbit inclined at about 29 degrees, at fixed longitudes over the Indian Ocean region. GSLV-F19 will leave the satellite in a transfer orbit, and NVS-04 will then use its own engine to climb to its station.

How many NVS satellites are planned?

ISRO has said five second-generation satellites, NVS-01 to NVS-05, are envisaged to strengthen the NavIC constellation. NVS-01 is in service, NVS-02 did not reach its orbit, NVS-03 launched in October 2026, and NVS-04 and NVS-05 are still to fly. No launch date has been announced for either.

Can I track NVS-04 live?

Not yet. NVS-04 has not launched, so there is no orbit and no position to show, and this page does not display a placeholder. Once it is in orbit and public orbital elements are published, it will appear with the other satellites on the NavIC satellite tracker.